L
Linda
My company is trying to recover from a very poorly implemented installation
of Project Server 2003. I was assigned to maintain the projects and server
content after the fact.
We are using timesheets. Resources are responsible for entering time daily
and "updating all" weekly. Project Managers were provided a global template
that made all tasks "Fixed Duration" because the company Project
Administrator thought fixed duration meant "Fixed Dates."
Project Managers were told to stop updating projects from timesheets after
the first update. This was because the project managers clicked "Accept All"
to do their updates and missed the fact that many resources entered time on
tasks that weren't supposed to start until months later. Or the server moved
Finish dates to earlier deadlines by applying the Max units from the Resource
Pool on every project so each resource was assigned 100 percent on all tasks
for all projects (which in turn, moved the dates when the work was
recalculated).
Needless to say, we had a very short training class for Project Managers,
and no training at all for resources to complete timesheets. I was lucky to
get an hour with a consultant so I could learn how to accept timesheets as a
resource admin. I had no real project management experience (except for
putting out fires like I'm doing now).
We had invited 2 consultants to come in and help us make things right.
Unfortunately, when management heard what it would take to make it right,
they weren't open to the suggestion. My heart goes out to those consultants
because I know they were right but we couldn't convince management.
Since then, no other tools have surfaced that will help us out of this mess
(as expected) without a major dollar investment. And now, I've been asked to
suggest a timesheet program since Project "isn't working."
I'm not ready to give up on MS Project Server, or Project Professional in
terms of Project Management. I know we can make it work if I can change the
organizational culture of "Project Managers should not have to spend more
than 2 hours a week maintaining their projects."
I want to push a plan for a proper implementation. I want to introduce a
plan that suggests we hire project managers who are skilled at maintaining
server projects, so our technical resources can focus on their "real job"
instead of project management. That will solve the problem of project
managers taking 2 hours a week on project management because the current
project managers would not have to do project management.
I want to include training for project managers and resources, by training
our training staff on how we will implement the second round of Project
Server so they can training PMs and resources.
But before I do all this, I need to be sure MS Project Server will do what
we need it to do. Unfortunately, we are a date driven organization and the
dates are decided by our legislature, not by us. Therefore; if we have to
work 24-hour days to get something done to meet a date, we have to do it.
So, obviously, we are a "Fixed Date" organization. (No one will admit to
meeting a deadline early, hahaha, with our workload.)
Approximately 80% of our regular work is maintanence programs where costs
must be captured by fiscal year--again, "fixed date" programs. But we do
have projects that are very large that are divided both by sub projects and
phases. These very large projects have many deliverables and sub projects
will end before the larger "parent" project is done. A phase may consist of
multiple sub projects that could end or continue after the phase is complete.
A "parent" project could take more than a year or two to complete.
My Question: Is there a way to organize our "fixed date" maintanence
programs with our projects that have specific deliverables with an MS Project
solution? We use only one project server for our department (because there
are approximately 15 projects on the server that share the same resources -
not including maintenance programs which also share the same resources.
There is only one big project on the server, but we have 2 more we are
currently working that were mandated where we don't have a way to track them
electronically.)
Would we be able to maintain programs where the dates won't move, while
maintaining projects where they do move? I don't want to throw the baby out
with the bathwater.
This is a common scenario, I know. But is there a common way I can fix it
(and sell it to management) without bankrupting the company?
What factors are used to determine when you should have more than one
server? If you don't have more than one server, how to you manage programs
and projects on the same server with one resource pool where the server won't
update Max Units on the resources for all plans? We're obviously doing this
all wrong. How do we do it right? Are there books I can read to help me
state my case?
Help!
of Project Server 2003. I was assigned to maintain the projects and server
content after the fact.
We are using timesheets. Resources are responsible for entering time daily
and "updating all" weekly. Project Managers were provided a global template
that made all tasks "Fixed Duration" because the company Project
Administrator thought fixed duration meant "Fixed Dates."
Project Managers were told to stop updating projects from timesheets after
the first update. This was because the project managers clicked "Accept All"
to do their updates and missed the fact that many resources entered time on
tasks that weren't supposed to start until months later. Or the server moved
Finish dates to earlier deadlines by applying the Max units from the Resource
Pool on every project so each resource was assigned 100 percent on all tasks
for all projects (which in turn, moved the dates when the work was
recalculated).
Needless to say, we had a very short training class for Project Managers,
and no training at all for resources to complete timesheets. I was lucky to
get an hour with a consultant so I could learn how to accept timesheets as a
resource admin. I had no real project management experience (except for
putting out fires like I'm doing now).
We had invited 2 consultants to come in and help us make things right.
Unfortunately, when management heard what it would take to make it right,
they weren't open to the suggestion. My heart goes out to those consultants
because I know they were right but we couldn't convince management.
Since then, no other tools have surfaced that will help us out of this mess
(as expected) without a major dollar investment. And now, I've been asked to
suggest a timesheet program since Project "isn't working."
I'm not ready to give up on MS Project Server, or Project Professional in
terms of Project Management. I know we can make it work if I can change the
organizational culture of "Project Managers should not have to spend more
than 2 hours a week maintaining their projects."
I want to push a plan for a proper implementation. I want to introduce a
plan that suggests we hire project managers who are skilled at maintaining
server projects, so our technical resources can focus on their "real job"
instead of project management. That will solve the problem of project
managers taking 2 hours a week on project management because the current
project managers would not have to do project management.
I want to include training for project managers and resources, by training
our training staff on how we will implement the second round of Project
Server so they can training PMs and resources.
But before I do all this, I need to be sure MS Project Server will do what
we need it to do. Unfortunately, we are a date driven organization and the
dates are decided by our legislature, not by us. Therefore; if we have to
work 24-hour days to get something done to meet a date, we have to do it.
So, obviously, we are a "Fixed Date" organization. (No one will admit to
meeting a deadline early, hahaha, with our workload.)
Approximately 80% of our regular work is maintanence programs where costs
must be captured by fiscal year--again, "fixed date" programs. But we do
have projects that are very large that are divided both by sub projects and
phases. These very large projects have many deliverables and sub projects
will end before the larger "parent" project is done. A phase may consist of
multiple sub projects that could end or continue after the phase is complete.
A "parent" project could take more than a year or two to complete.
My Question: Is there a way to organize our "fixed date" maintanence
programs with our projects that have specific deliverables with an MS Project
solution? We use only one project server for our department (because there
are approximately 15 projects on the server that share the same resources -
not including maintenance programs which also share the same resources.
There is only one big project on the server, but we have 2 more we are
currently working that were mandated where we don't have a way to track them
electronically.)
Would we be able to maintain programs where the dates won't move, while
maintaining projects where they do move? I don't want to throw the baby out
with the bathwater.
This is a common scenario, I know. But is there a common way I can fix it
(and sell it to management) without bankrupting the company?
What factors are used to determine when you should have more than one
server? If you don't have more than one server, how to you manage programs
and projects on the same server with one resource pool where the server won't
update Max Units on the resources for all plans? We're obviously doing this
all wrong. How do we do it right? Are there books I can read to help me
state my case?
Help!