S
Subramanian Vasudevan
Hi,
I'm having a problem when using QueueAddtoProject to add tasks and
assignments to a blank project.
Here's the text of the Queue Error I get:
Message:'MSP : Queue request Failed for Job ID
3cbbad1d-263e-4fbc-b74e-bb4f06dff0e6.
<?xml version="1.0" encoding="utf-16"?>
<errinfo>
<general>
<class name="Project">
<error id="9133" name="ProjectSchedulingEngineException"
uid="50ba33e1-6500-49c1-8aad-ecfd43c5e969"
exception="Microsoft.Office.Project.Scheduling.SchedulingException: Cannot
extend beyond minimum date
at
Microsoft.Office.Project.Server.BusinessLayer.ProjectSchedule.Schedule()
at
Microsoft.Office.Project.Server.BusinessLayer.ProjectMain.HandleProject(ProjectDataSet
dataset, Guid projectUid, Guid userUid, String userName, Boolean isNew,
Boolean addColumns, ProjectLocks projectLock, Boolean CheckReadOnly, Boolean
fCheckProtectedActuals, Boolean
fAllowAddEntRes, Boolean fOptIndexRecalced)" />
</class>
<class name="Queue">
<error id="26000" name="GeneralQueueJobFailed"
uid="0044e41a-9645-4d6f-a80c-5becd2ecded4"
JobUID="3cbbad1d-263e-4fbc-b74e-bb4f06dff0e6" ComputerName="AU
I do NOT set any of the Task Start Dates, and I have no constraints on them
to dictate the schedule. I have set the Project Start Date though, so I
expect the Task Start Dates to default to this date.
Everything happens fine for most cases of Projects I create, but the above
error occurs when I have some assigments on Labour Resources whose ASSN_WORK
is very huge, extending over couple of DECADES of work.
It is absolutely essential that I fix this soon. Huge assignment work data
is very much possible in the business I want to integrate Project with.
Thanks and Regards,
Subramanian Vasudevan
PS: I have the Service Pack 1, the August CU and the Infrastructure update
installed.
PPS: I dont use any custom fields anywhere, so the problem cant be due to
that. I also dont change the TASK_OUTLINE_LEVEL, because everythime, its a
brand new project and I use QueueAddtoProject.
I'm having a problem when using QueueAddtoProject to add tasks and
assignments to a blank project.
Here's the text of the Queue Error I get:
Message:'MSP : Queue request Failed for Job ID
3cbbad1d-263e-4fbc-b74e-bb4f06dff0e6.
<?xml version="1.0" encoding="utf-16"?>
<errinfo>
<general>
<class name="Project">
<error id="9133" name="ProjectSchedulingEngineException"
uid="50ba33e1-6500-49c1-8aad-ecfd43c5e969"
exception="Microsoft.Office.Project.Scheduling.SchedulingException: Cannot
extend beyond minimum date
at
Microsoft.Office.Project.Server.BusinessLayer.ProjectSchedule.Schedule()
at
Microsoft.Office.Project.Server.BusinessLayer.ProjectMain.HandleProject(ProjectDataSet
dataset, Guid projectUid, Guid userUid, String userName, Boolean isNew,
Boolean addColumns, ProjectLocks projectLock, Boolean CheckReadOnly, Boolean
fCheckProtectedActuals, Boolean
fAllowAddEntRes, Boolean fOptIndexRecalced)" />
</class>
<class name="Queue">
<error id="26000" name="GeneralQueueJobFailed"
uid="0044e41a-9645-4d6f-a80c-5becd2ecded4"
JobUID="3cbbad1d-263e-4fbc-b74e-bb4f06dff0e6" ComputerName="AU
I do NOT set any of the Task Start Dates, and I have no constraints on them
to dictate the schedule. I have set the Project Start Date though, so I
expect the Task Start Dates to default to this date.
Everything happens fine for most cases of Projects I create, but the above
error occurs when I have some assigments on Labour Resources whose ASSN_WORK
is very huge, extending over couple of DECADES of work.
It is absolutely essential that I fix this soon. Huge assignment work data
is very much possible in the business I want to integrate Project with.
Thanks and Regards,
Subramanian Vasudevan
PS: I have the Service Pack 1, the August CU and the Infrastructure update
installed.
PPS: I dont use any custom fields anywhere, so the problem cant be due to
that. I also dont change the TASK_OUTLINE_LEVEL, because everythime, its a
brand new project and I use QueueAddtoProject.