Projectwise Resource Engaged & Availability report

T

TheRock

Hi, I am new to MSP & MSPWA. We generally use MSP & PWA to manage our
projects. Now we require a report that shows status (Allocated and Available)
of all active resources on a particular day or daywise. Is there any existing
report for it or how can it be developed? Please help me out.
 
B

Barbara Henhapl

Hi,

a tip for your next question: to get answers for project server questions,
it is better to ask in microsoft.public.project.server.

There are several methods to see what you want to see. Depends if you want
to have a graphical overview, on the number of your active resources, ....
1. PWA - Resource Center - Actions - Select All Resources. Click on View
Availability. Red line will show availability. You can switch between
different views, perhaps some will be what you are looking for?
2. If your OLAP Cube is configured and running an a regular basis, you can
create a Data Analysis View. Server Settings - Manage Views - New View.
Scroll down to view definition. Move totals from the field list to the
yellow part, in your case it could be capacity and work. Add Project List
and/or Resource List to Filter/Row or Columns. Add 'Time' as Filter or
Column. If your field lsit is hidden, get it bach by acticating "Show Field
List". Define appropriate categories and a name and save.
3. Write a report with reporting services.

Does any of these help?

Regards
Barbara
 