Projekt 2003, assignment departing, on the gantt-diagram trouble

L

Lasse

Hi

I have a problem on some projekts documents. In some of the documents I can´t depart the assignments i two parts so they have different start and end dates. When I have to depart one assignment in two sections in some of my documents i won´t. Unlike if I start a new document.

Hope You are able to hel

Thanks!
 
M

Mike Glen

Hi Lasse,

Welcome to this Microsoft Project newsgroup :)

If I understand you correctly, you are unable to show split tasks. Try
Format/Layout.../and check the box to Show bar splits.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top