L
Luc Gestin
I have a Master Project schedule and inserted sub-projects (with the MS
Project Insert function).
I have linked milestones in sub-projects (sub-project milestone) to
milestones in Master Project (Master Project milestone).
When I update a sub-project milestone at 100% complete, there is no impact
on the linked Master Project milestone. I was expecting that this Master
Project milestone would automatically become 100% complete.
It seems that %Complete data gets propagated between sub-projects and Master
Program only when I use Copy Cell/Paste Special/Link Data function on the
%Complete field.
Any advice would be very much appreciated. Thanks.
Kind regards.
Project Insert function).
I have linked milestones in sub-projects (sub-project milestone) to
milestones in Master Project (Master Project milestone).
When I update a sub-project milestone at 100% complete, there is no impact
on the linked Master Project milestone. I was expecting that this Master
Project milestone would automatically become 100% complete.
It seems that %Complete data gets propagated between sub-projects and Master
Program only when I use Copy Cell/Paste Special/Link Data function on the
%Complete field.
Any advice would be very much appreciated. Thanks.
Kind regards.