Hi,
I'm trying to figure out how MS Project Server 2007 works when it comes to
Proposals.
We have a proposal that where we have defined some work/ task details and
assigned some resources to it. Aslo, we have created a Resource plan with
the same resources and specified a different committment, set the 'Calculate
resource utilization from" option to 'Resource Plan'.
When we go to PWA 'View Assignments" the resources show the work that we
entered in the work/ details part of the proposal. When we go to PWA 'View
Availability' we see the hours we entered in the 'Resource plan' for the
proposal.
Is this discrepancy between the View Assignments and View Availability
normal? If so, what is the reasoning?
/Spiro Theopoulos
I'm trying to figure out how MS Project Server 2007 works when it comes to
Proposals.
We have a proposal that where we have defined some work/ task details and
assigned some resources to it. Aslo, we have created a Resource plan with
the same resources and specified a different committment, set the 'Calculate
resource utilization from" option to 'Resource Plan'.
When we go to PWA 'View Assignments" the resources show the work that we
entered in the work/ details part of the proposal. When we go to PWA 'View
Availability' we see the hours we entered in the 'Resource plan' for the
proposal.
Is this discrepancy between the View Assignments and View Availability
normal? If so, what is the reasoning?
/Spiro Theopoulos