B
BJB
We are using Project Server 2007 and our default reporting status is %
complete instead of actual hours. Our IT organization wants the entire PMO to
switch to reporting actual hours (and allowing the PMs to change this on a
per project basis). The reason for the change is because they are telling us
that in order to use proposals and activities we have to make this change. I
haven't used these capabilities (I prefer setting up projects instead for a
wide variety of reasons) so I don't know if this "restriction" is true. We
have not enabled timesheets.
Thanks for any help
complete instead of actual hours. Our IT organization wants the entire PMO to
switch to reporting actual hours (and allowing the PMs to change this on a
per project basis). The reason for the change is because they are telling us
that in order to use proposals and activities we have to make this change. I
haven't used these capabilities (I prefer setting up projects instead for a
wide variety of reasons) so I don't know if this "restriction" is true. We
have not enabled timesheets.
Thanks for any help