M
Mike F
Using MSP2007 connected to Server. I can only get the proposed booking type
to toggle between Committed and Proposed for a resoruce through "Build
Team..." and not within a project at a task by task level by inserting the
column booking type. Any guidance would be appreciated.
Senario: I am wanting to publish a project that only has the requirements
section of the plan committed and ready to take progress and the remainder of
the plan is still gathering estimates and resources. I only want to capture
task progress and report availability on the committed resoruces to selected
tasks.
to toggle between Committed and Proposed for a resoruce through "Build
Team..." and not within a project at a task by task level by inserting the
column booking type. Any guidance would be appreciated.
Senario: I am wanting to publish a project that only has the requirements
section of the plan committed and ready to take progress and the remainder of
the plan is still gathering estimates and resources. I only want to capture
task progress and report availability on the committed resoruces to selected
tasks.