Proposed booking type

J

JB

I have a project that we need to remove from everyone's time sheet.
So I have changed the booking type from committed to Proposed, then
republished the schedule. For some reason, this did not remove the
assignments.

I followed these same steps on a different project, with success.

Any ideas?
 
A

ahelp

Hi JB,
Try reducing the remaining work to zero & ensuring the % Complete is 100%.
If you use managed timesheets, the first time you publish, don't synch to
timesheets. Once you've pushed the zero remaining work out to timesheets, you
can synch.
 
D

Dale Howard [MVP]

JB --

Is the project in question an Administrative project by chance? If so,
using the Proposed booking type will not remove the tasks from each user's
View My Tasks page in PWA. The only way to remove those administrative
tasks is to save the project as an .mpp file and then delete it from the
Project Server database. Let us know if this helps.
 
J

JB

JB --

Is the project in question an Administrative project by chance? If so,
using the Proposed booking type will not remove the tasks from each user's
View My Tasks page in PWA. The only way to remove those administrative
tasks is to save the project as an .mpp file and then delete it from the
Project Server database. Let us know if this helps.










- Show quoted text -

No this is not an administrative project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top