Proposed bookings and resource availability

A

Andre

I am using proposed bookigs for several projects. The resource
availability view in PWA does not seem to work properly with this
feature. When unchecking the proposed booking box the graph still shows

the resource's work in the project that he has a proposed booking in.
It´s as if the planned work is not shown, but the resource's
availibility. At the same time, the red line showing the availability
of the resource disappears.
Is this a known bug, or am I doing something wrong.
BTW, the OLAP cube has been updated and for the time periods that this
concerns the resource availibility is als published.


André
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question