Proposed Resources and the cube reports

M

maryann

I believe that I understand the use of "Proposed"
vs. "Committed" resources during the Build team from
Enterprise phase, and see that the availability charts in
these views give the option to reflect this distinction.

I'm confused how this label translates to the Portfolio
Analyzer cube, however. From my testing, any work assigned
to a resource, regardless of whether it is tagged as
Proposed or Committed, appears in the cube reports. Is
there any way, short of defining filtering on some Ent
Outline Code, to filter based on this tag?

thanks
 
G

Gary L. Chefetz \(MVP\)

Maryann:

To distinguish the amount of hours committed versus booked in the Portfolio
Analyzer, you use the Booking Type dimension in your view.

--

Gary L. Chefetz, MVP
"We wrote the book on Project Server
http://www.msprojectexperts.com

-
 