S
SPM
For some reason time on proposed tasks are being added to the resource
work load and affecting availability. Does anyone have an explanation
or solution for this issue?
Here is some sample data with the upper row being the summary totals.
Committed 864 hrs 11.22h 10.4h 9.5h 8.4h 15.65h
Committed 56 hrs
Committed 80 hrs
Committed 120 hrs 2.82h 2h 1.1h
Committed 8 hrs 0.4h 0.4h 0.4h 0.4h 0.02h
Committed 80 hrs 7.63h
Committed 360 hrs 0h 0h 0h 0h 0h
Committed 0 hrs
Proposed 160 hrs 8h 8h 8h 8h 8h
As you can see, it is adding the proposed as well.
Any help would be appreciated
Thanks,
SPM
work load and affecting availability. Does anyone have an explanation
or solution for this issue?
Here is some sample data with the upper row being the summary totals.
Committed 864 hrs 11.22h 10.4h 9.5h 8.4h 15.65h
Committed 56 hrs
Committed 80 hrs
Committed 120 hrs 2.82h 2h 1.1h
Committed 8 hrs 0.4h 0.4h 0.4h 0.4h 0.02h
Committed 80 hrs 7.63h
Committed 360 hrs 0h 0h 0h 0h 0h
Committed 0 hrs
Proposed 160 hrs 8h 8h 8h 8h 8h
As you can see, it is adding the proposed as well.
Any help would be appreciated
Thanks,
SPM