A
Andrea
Hi all again!
A question about the strange behavour of Project when you work with a
"generic resource".
Scenario: MSP2003, PServer2003. In a plan i've got some tasks and some
resource=user and 1 generic resource. The resources=users use the Timeshhet
for submit their own actual hours. The Generic is directly updated by the
Project Manager in Project Professional.
I've the "manage periods" set it up.
When the PM writes a value in the Actual Work field for the Generic , the
system tells him about OUT OF SYNCH....My opinion this is a non-correct
message....a generic resource is a "external"...is a consultant..is a
skill..so the Generic does't have to submit any kind of TImesheet...and so no
protected actual should be saved.
What's ur opinion??
Bye
Andrea
A question about the strange behavour of Project when you work with a
"generic resource".
Scenario: MSP2003, PServer2003. In a plan i've got some tasks and some
resource=user and 1 generic resource. The resources=users use the Timeshhet
for submit their own actual hours. The Generic is directly updated by the
Project Manager in Project Professional.
I've the "manage periods" set it up.
When the PM writes a value in the Actual Work field for the Generic , the
system tells him about OUT OF SYNCH....My opinion this is a non-correct
message....a generic resource is a "external"...is a consultant..is a
skill..so the Generic does't have to submit any kind of TImesheet...and so no
protected actual should be saved.
What's ur opinion??
Bye
Andrea