M
MAT
Hi.
What is the difference between "Protected actual work" and "actual work" in
PWA. and why do I have the "actual work"= zero for new createt Views in
Project center?
I mean in some of the Projectcenter views the field "actual work" shows the
right value. Wenn I create a new view, it si always 0. I have to use the
field "Protectet actal work".
Thanks...
What is the difference between "Protected actual work" and "actual work" in
PWA. and why do I have the "actual work"= zero for new createt Views in
Project center?
I mean in some of the Projectcenter views the field "actual work" shows the
right value. Wenn I create a new view, it si always 0. I have to use the
field "Protectet actal work".
Thanks...