R
Rob Beckman
We use managed time periods with MSPS '03.
I ran across a project that stopped showing up in the OLAP cube so I started
digging into it a little further and noticed that the project actuals in the
project plan are all zero (0) now even though the actual work has time it.
I've tried synching with actuals and it does it but they are still 0.
There's no time outstanding and this only started happening a couple of
weeks ago and the project is several months old.
Any ideas on how to get the protected actuals back out there?
I'm figuring once the protected actuals get out there the OLAP problem
should resolve itself too. If that's a bad assumption I'd I'm ears on what
we can do to fix that too.
Thanks
Rob
I ran across a project that stopped showing up in the OLAP cube so I started
digging into it a little further and noticed that the project actuals in the
project plan are all zero (0) now even though the actual work has time it.
I've tried synching with actuals and it does it but they are still 0.
There's no time outstanding and this only started happening a couple of
weeks ago and the project is several months old.
Any ideas on how to get the protected actuals back out there?
I'm figuring once the protected actuals get out there the OLAP problem
should resolve itself too. If that's a bad assumption I'd I'm ears on what
we can do to fix that too.
Thanks
Rob