J
Johnnie
I have a manager who created a new schedule by copying an older one with
simular tasks and resources. The problem now is that we are trying to delete
un-necessary resources, but can not because Project indicates the resources
can not be deleted because there protected actuals although there is no
actual work. Is there a way to turn this option on or off? We use MS
Project Server 2003. Thanks for your help.
Johnnie
simular tasks and resources. The problem now is that we are trying to delete
un-necessary resources, but can not because Project indicates the resources
can not be deleted because there protected actuals although there is no
actual work. Is there a way to turn this option on or off? We use MS
Project Server 2003. Thanks for your help.
Johnnie