J
JoeP
I have a resource who is doing work for multiple, related projects. He can
only invest 50% of his time (e.g., 4 hours/day) across all of these projects.
So as a simple example, if each of the four projects require four hours of
his time, the Resource Usage view would show him spending four hours per day
for four days.
I think what I need to do is have this resource in a master project, and
have all the projects he is working on be linked into this master as
subprojects.
Will this meet my need? What other things must I do to ensure this resource
does not get overallocated and all Finish Dates correctly uphold his 50%
allocation constraint?
only invest 50% of his time (e.g., 4 hours/day) across all of these projects.
So as a simple example, if each of the four projects require four hours of
his time, the Resource Usage view would show him spending four hours per day
for four days.
I think what I need to do is have this resource in a master project, and
have all the projects he is working on be linked into this master as
subprojects.
Will this meet my need? What other things must I do to ensure this resource
does not get overallocated and all Finish Dates correctly uphold his 50%
allocation constraint?