We are implementing PS2007. During system testing with a published project
and using Enterprise Resources, the Project Web Access Assignment Details
Page appears "locked" so that the assigned resource cannot update any field,
including the Remaining Work field. The tasks were imported from the
Timesheet. This is true for three different resources assigned to tasks in
the project. With previous installs all these Assignmt Detail fields were
updatable. All other PWA functions appear to work fine. If the resource
uses the Outlook Sync, however, the resource can update the Task's Remaining
Work field in Outlook and submit the update to PWA. In this instance, the
Remaining Work then updates in PWA. Has anyone had experience with this
issue or can suggest a possible solution?
Thanks, Terry
and using Enterprise Resources, the Project Web Access Assignment Details
Page appears "locked" so that the assigned resource cannot update any field,
including the Remaining Work field. The tasks were imported from the
Timesheet. This is true for three different resources assigned to tasks in
the project. With previous installs all these Assignmt Detail fields were
updatable. All other PWA functions appear to work fine. If the resource
uses the Outlook Sync, however, the resource can update the Task's Remaining
Work field in Outlook and submit the update to PWA. In this instance, the
Remaining Work then updates in PWA. Has anyone had experience with this
issue or can suggest a possible solution?