C
Chris M
We are encountering some situations on projects that on a particular task,
the units for a given resource went from say, 50% allocation to 1,200,000%
and the other has 358%. The task has a number of resources assigned to it,
and it tends to happen to 1 -2 resources out of the 8 that might be assigned
to the task. Our tasks are Fixed work, effort driven tasks. This particular
task has a FF relationship to others. I can't quite figure out what's
causing this. I've tried doing the whole work x units = duration thing, but
my math is not working out. Has anyone seen this? The impact of this is
causing out dates to 'zing' out to the future.
Thanks!
the units for a given resource went from say, 50% allocation to 1,200,000%
and the other has 358%. The task has a number of resources assigned to it,
and it tends to happen to 1 -2 resources out of the 8 that might be assigned
to the task. Our tasks are Fixed work, effort driven tasks. This particular
task has a FF relationship to others. I can't quite figure out what's
causing this. I've tried doing the whole work x units = duration thing, but
my math is not working out. Has anyone seen this? The impact of this is
causing out dates to 'zing' out to the future.
Thanks!