Hi-
My client is using %Complete as their task progress reporting option. I
have not been able to figure out a way to allow them to change the duration
of a task in progress using this environment (I can only see a way to do it
once the task is 100% complete). The Start Date always floats with the
Finish Date if the Finish Date is changed. The Units field is not editable
if I add it to the Assignment Details view, and the Duration field is not
available in this view.
Any thoughts are much appreciated-
Beth
My client is using %Complete as their task progress reporting option. I
have not been able to figure out a way to allow them to change the duration
of a task in progress using this environment (I can only see a way to do it
once the task is 100% complete). The Start Date always floats with the
Finish Date if the Finish Date is changed. The Units field is not editable
if I add it to the Assignment Details view, and the Duration field is not
available in this view.
Any thoughts are much appreciated-
Beth