When you are working with multiple projects (and the same resources on all
the projects), what is the best process for creating projects and baselining
/ tracking progress?
Should we:
1. Create the project and baseline it with NO leveling
2. Create the project and level it alone and then baseline it
3. Create the project, add it to a master project that holds the other
projects, level it along with other projects and then baseline it?
Thanks for ideas on this.
the projects), what is the best process for creating projects and baselining
/ tracking progress?
Should we:
1. Create the project and baseline it with NO leveling
2. Create the project and level it alone and then baseline it
3. Create the project, add it to a master project that holds the other
projects, level it along with other projects and then baseline it?
Thanks for ideas on this.