It looks like the SP2 is not able to pick up the outline codes values from an
SP1 MPP file.
When opening a MPP that was created in SP1 in our SP2 environment, the
outline codes values are incorrect. The testers are having to go into the
outline codes and re-enter the correct information. Has anyone had the same
issues.
Example - if you choose Project - Project Information - the baseline Year
is incorrect and some of our custom outline codes values are incorrect.
SP1 MPP file.
When opening a MPP that was created in SP1 in our SP2 environment, the
outline codes values are incorrect. The testers are having to go into the
outline codes and re-enter the correct information. Has anyone had the same
issues.
Example - if you choose Project - Project Information - the baseline Year
is incorrect and some of our custom outline codes values are incorrect.