PS03 - Timesheet Periods don't scroll

T

TroyS

A recent install of PS03 with SP3 applied
I have managed periods set up and i've created 3

I tested the project publishing by creating a 1d task and assigning a person
to the task.
Initially, the timesheet showed the one day but i could not scroll forwards
or backwards.

i then updated the project schedule for somehting like 10d duration and
republished.
The timesheet will still not scrolll forwards/backwards though the timesheet
periods are defined.
Also, i cannot select the dates and use Set Dates ... even though the
calendar appears, when i try selecting the date, nothing is entered. Even if
i type in the dates and use set dates, the timesheet period does not
advance.

Any ideas on what i've overlooked?
thx.
 