EPMLearner
Ok, he is my dilema:
I have three resources that will work 1/1/09 to 2/28/09 10 hours a day
5-days a week.
Our standard calendar is set to a 8 hour per day, 5day per week calendar.
When I try to set up calendars via Resource Center by selecting the resource
(open with Microsoft Project), double click the resource I want, Change
Working Time, Work Weeks and create a new line called 50 hour work week, I
enter the specific dates, and click on details to set the times --> MS
project crashes. So I then try to go in another way. I go to Server
Settings-->Enterprise Calendars and set up a 50 hour work week Calendar but
for whatever reason the data that I enter regarding the hours does not
retain. It ends up defaulting back to a 8 hr/40 hr work week.
Any suggestions?
I have three resources that will work 1/1/09 to 2/28/09 10 hours a day
5-days a week.
Our standard calendar is set to a 8 hour per day, 5day per week calendar.
When I try to set up calendars via Resource Center by selecting the resource
(open with Microsoft Project), double click the resource I want, Change
Working Time, Work Weeks and create a new line called 50 hour work week, I
enter the specific dates, and click on details to set the times --> MS
project crashes. So I then try to go in another way. I go to Server
Settings-->Enterprise Calendars and set up a 50 hour work week Calendar but
for whatever reason the data that I enter regarding the hours does not
retain. It ends up defaulting back to a 8 hr/40 hr work week.
Any suggestions?