PS07 My Tasks - 1st Progress day is always Monday

T

TroyS

Have PS07 + SP1 along with MOSS in a server farm.
We are updating Tasks with Actual Hours per Period.

No matter what day of the week i put in PWA Server Settings for the week to
start on, (say Sunday), I always see Monday as listed first in My Tasks.
This is true for all users of PWA... Though if i go to MS Project 2007, the
week starts on Sunday ...

I"ve looked at the settings on the My Tasks Web part and nothing is there
except selecting an Hours by Day option.

any ideas? Is this fixed in the IU or a CU update?
 