T
TroyS
I have PS07 with Dec CU
We are using My Tasks to update the project; we are not using My Timesheets
We've noticed that time approved from team members assigned to tasks is not
showing in the project schedule.
1) If you look at PWA My Tasks for the individuals, all zeroes
2) If you drill into the task from PWA My Tasks, the grid shows Actual Work
as 0h
3) If you look at the submitted and approved notes below you can see the PM
approved the hours on specific days and what the Actual Work hr were
4) If you go to the PM and have the drill into the Reviewed and Approved
hours from PWA the same information across team members shows Actual Work
being submitted and approved
5) However, the task in question in the project schedule shows zero Actual
Work
We did not delete and recreate any tasks in the project
We did not have any 'event' where we had to restore a database or a server
farm.
Any ideas on what this is all about?
and How do we get the already-approved hours (Per PWA) into the plan and
published back out?
thx.
We are using My Tasks to update the project; we are not using My Timesheets
We've noticed that time approved from team members assigned to tasks is not
showing in the project schedule.
1) If you look at PWA My Tasks for the individuals, all zeroes
2) If you drill into the task from PWA My Tasks, the grid shows Actual Work
as 0h
3) If you look at the submitted and approved notes below you can see the PM
approved the hours on specific days and what the Actual Work hr were
4) If you go to the PM and have the drill into the Reviewed and Approved
hours from PWA the same information across team members shows Actual Work
being submitted and approved
5) However, the task in question in the project schedule shows zero Actual
Work
We did not delete and recreate any tasks in the project
We did not have any 'event' where we had to restore a database or a server
farm.
Any ideas on what this is all about?
and How do we get the already-approved hours (Per PWA) into the plan and
published back out?
thx.