TroyS
because we are managing some tasks for Task/Hour Updates and other tasks
mainly as %Complete, we don't have all tasks Published = Yes.
Is there a way in the olap cube, timephased data (eg MSP Portfolio
Analyzer), to get this field in there? If MDX, what would the expression be?
I tried using a formula task field = [Publish] but formulas don't show in
OLAP
mainly as %Complete, we don't have all tasks Published = Yes.
Is there a way in the olap cube, timephased data (eg MSP Portfolio
Analyzer), to get this field in there? If MDX, what would the expression be?
I tried using a formula task field = [Publish] but formulas don't show in
OLAP