PS07 - Task Published? = Yes in Data Analysis

T

TroyS

because we are managing some tasks for Task/Hour Updates and other tasks
mainly as %Complete, we don't have all tasks Published = Yes.

Is there a way in the olap cube, timephased data (eg MSP Portfolio
Analyzer), to get this field in there? If MDX, what would the expression be?

I tried using a formula task field = [Publish] but formulas don't show in
OLAP
 
M

Marc Soester [MVP]

Troy, MDX allone wont do it, you will need to extend the cube which requires
custom dev. Check out the Project Server SDK for some examples
hope this helps
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top