PS07 Task Updates performed in Timephased View and actual hours mo

J

JP

We use PS07 and update our tasks daily via the My Tasks page and the
Timephased view. The task updates are typically accepted everyday and the
projects are published via the publish feature on the 'Applied Task Update
Requests and Errors' page.

Then we're seeing that hours submitted one day are not there the next day in
the resources 'My Tasks' view, or they have moved to other days and have
weird hours. When the project plan is opened in Project Professional, the
actual hours do not match what was updated and they do not match what PWA
currently shows.

Does anyone have an idea of what is causing this problem?

(note: we have made all the current available updates to both project server
and project professional)
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top