PS2003 actual work and actual work protected

J

JennPenn07

I attempted to sync the work on the admin schedule ….
Even after I did, they are still out of sync.
Any ideas on how to fix?
 
J

Jonathan Sofer [MVP]

I would first make sure you are on the latest service pack of PS2003 server
and client?

After that, if synching actuals does not work, the only alternative I am
aware of is to temporarily turn off protected actuals and to republish the
schedule with "Overwrite actuals" enabled to force the actuals in the
schedule to push out to the timesheets in PWA. Then turn on protected
actuals again.
 
J

Jonathan Sofer [MVP]

I agree, that would be ideal. Have you validated you are on the latest and
greatest service packs, updates, etc for both the client and the server?
 
J

JennPenn07

yes, sp3 for both client and server.

Jonathan Sofer said:
I agree, that would be ideal. Have you validated you are on the latest and
greatest service packs, updates, etc for both the client and the server?
 
J

JennPenn07

I've been able to narrow down the tasks that are not synching, what affect
would it have on my plan if we manually enter the values?

Doesn't the sync tool do the same thing?
 
J

JennPenn07

Ok, i forgot about managed time periods.

JennPenn07 said:
I've been able to narrow down the tasks that are not synching, what affect
would it have on my plan if we manually enter the values?

Doesn't the sync tool do the same thing?
 