P
Paul Miller
Our company use a package for managing absence requests, holiday, sickness etc.
When the project team request holiday, they have to do so in our absence
package, then inform the PS2003 administrator who changes the necessary
calendar to be a non-working time for the relevant period. This is open to
the obvious human errors which occur frequently.
Using an administrative project works well for time-sheet logging, but not
very well for forward planning, levelling etc.
I would like to take the data from the absence system and automatically
update the SQL tables behind PS2003 to remove the manual process. Does anyone
have any details on how to do this as I cannot see how this information is
held within the project server database.
Thanks
When the project team request holiday, they have to do so in our absence
package, then inform the PS2003 administrator who changes the necessary
calendar to be a non-working time for the relevant period. This is open to
the obvious human errors which occur frequently.
Using an administrative project works well for time-sheet logging, but not
very well for forward planning, levelling etc.
I would like to take the data from the absence system and automatically
update the SQL tables behind PS2003 to remove the manual process. Does anyone
have any details on how to do this as I cannot see how this information is
held within the project server database.
Thanks