JennPenn07
Project Server 2003 sp3
resources adds themself to a task and submits the task. PM tries to accept
but get an error msg that says "Cannot delete or reassign task or assignments
with protected actuals."
Any idea what we are doing wrong?
resources adds themself to a task and submits the task. PM tries to accept
but get an error msg that says "Cannot delete or reassign task or assignments
with protected actuals."
Any idea what we are doing wrong?