Hours from timesheets are not posting to the projects. We have tried
different things and can't seem to make it work. Our PS2003 has no problems
at all with this. Our PS2007 is a new system and we are starting out from
scratch -- so no contamination due to data migration. Everything else seems
to be working fine.
The project was created when PS2007 had the setting for marking completion
with a percentage. We changed that to entering hours and remaining hours,
then republished the project. This is happening to all our projects,
consistently.
We are hoping that we have overlooked some setting or such.
Any information would be appriciated.
HMHart
Crawford and Company
Atlanta, GA
MSMing
Broadspire
Lake Zurich, IL
(e-mail address removed)
different things and can't seem to make it work. Our PS2003 has no problems
at all with this. Our PS2007 is a new system and we are starting out from
scratch -- so no contamination due to data migration. Everything else seems
to be working fine.
The project was created when PS2007 had the setting for marking completion
with a percentage. We changed that to entering hours and remaining hours,
then republished the project. This is happening to all our projects,
consistently.
We are hoping that we have overlooked some setting or such.