PS2007 Actual hours not posting to project

M

Mac Hart

Hours from timesheets are not posting to the projects. We have tried
different things and can't seem to make it work. Our PS2003 has no problems
at all with this. Our PS2007 is a new system and we are starting out from
scratch -- so no contamination due to data migration. Everything else seems
to be working fine.

The project was created when PS2007 had the setting for marking completion
with a percentage. We changed that to entering hours and remaining hours,
then republished the project. This is happening to all our projects,
consistently.

We are hoping that we have overlooked some setting or such.

Any information would be appriciated.

HMHart
Crawford and Company
Atlanta, GA

MSMing
Broadspire
Lake Zurich, IL
(e-mail address removed)
 
R

Rod Gill

Hi,

Project Server 2007 has both Timesheets and My Tasks. Only My Tasks updates
projects. However, you can import hours from My Tasks to timesheets and from
Timesheets to My Tasks. The key difference between the two is that
Timesheets records Admin time as well and only My Tasks updates proejcts.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top