I am wanting to use the timesheet or calendar exception method for allocating
non-project time (e.g. vacation, training, sick) to resources. This seems to
work well enough however the details do not show up in either the
availability or assignment views. I have been asked where project manager's
can get a detailed view of competing resource allocations (project + non
project) when trying staff up projects. An example is that training might
need to be re-scheduled if the PM requires that resource for more pressing
work. Anybody know how to get a consolidated view of resource allocations
(assignments + timesheets)?
non-project time (e.g. vacation, training, sick) to resources. This seems to
work well enough however the details do not show up in either the
availability or assignment views. I have been asked where project manager's
can get a detailed view of competing resource allocations (project + non
project) when trying staff up projects. An example is that training might
need to be re-scheduled if the PM requires that resource for more pressing
work. Anybody know how to get a consolidated view of resource allocations
(assignments + timesheets)?