B
Bernie E
We're using PS2007 SP1. All of our tasks are fixed units. Resources are
using the My Tasks view to update actual and remaining time. The weird
thing is that the Assignment Units for each of the assignments keeps growing
each day to ridiculously high values. For example, one resource has a
60-hour assignment that shows 648.65 units. The PM is accepting task
updates and publishing each day, but is not changing the units for the tasks.
It seems PS2007 is doing this.
What is going on? Any ideas?
Thanks in advance.
Bernie
using the My Tasks view to update actual and remaining time. The weird
thing is that the Assignment Units for each of the assignments keeps growing
each day to ridiculously high values. For example, one resource has a
60-hour assignment that shows 648.65 units. The PM is accepting task
updates and publishing each day, but is not changing the units for the tasks.
It seems PS2007 is doing this.
What is going on? Any ideas?
Thanks in advance.
Bernie