Hi,
I am in a midst of migrating previous version project plans to PS2007, the
objective is to create and group the projects to a master plan. After I group
all the project plan to a master project, how could I perform a baseline on
the master project that refers to the projects' baseline information instead
of the projects' planned information?
Regards
Godrid