T
TroyS
In Project Server 2007, is there a 'best' or 'better' way to enter nonworking
time?
It doesn't seem you can double click a day to mark it as nonworking (as you
could in PS2003), but have to enter it on the Exceptions tab. then i've been
entering as:
New Years 2007
Martin Luther King 2007
Presidents Day 2007
etc, etc, etc
As there will be different days of the year for MLK and Presidents Day, then
I would need to come back for 2008 and enter similarly for those days rather
than change the entry made for MKL 2007 to be in 2008.
Just wondering if this is the way MS intended to work or if i'm overlooking
something. Seems odd that you can no longer double click a day and mark it as
nonworking.
btw, i'm using the Standard calendar...
time?
It doesn't seem you can double click a day to mark it as nonworking (as you
could in PS2003), but have to enter it on the Exceptions tab. then i've been
entering as:
New Years 2007
Martin Luther King 2007
Presidents Day 2007
etc, etc, etc
As there will be different days of the year for MLK and Presidents Day, then
I would need to come back for 2008 and enter similarly for those days rather
than change the entry made for MKL 2007 to be in 2008.
Just wondering if this is the way MS intended to work or if i'm overlooking
something. Seems odd that you can no longer double click a day and mark it as
nonworking.
btw, i'm using the Standard calendar...