PS2007 - Completed Projects

D

Dale Howard [MVP]

James --

Your Project Server administrator can manually or automatically back up all
enterprise projects to the Archive database. He/she can then delete the
enterprise project from the Draft and Published databases, as needed. Hope
this helps.
 
J

James Culshaw

This seems to 'backup' all projects in the database.

Is this the best way to do things. I guess we can still see the archived
projects by opening the project plan from the archive database. What happens
to the Workspaces though?
 
N

NZ Projects

Project Server archiving does not accomodate WSS sites. You can choose to
delete WSS sites (or not) when you delete the projects.
 
J

James Culshaw

What happens to the resource allocation and timesheet entries when I delete
the project from the published database after archiving?

James :)
 
N

NZ Projects

My understanding is that the timesheet info will be retained, but any
assignment info will be deleted with the project.
 