K
Kerry
It gets there, it just doesn't get back. We have several PM's having sync
problems between MS Project and Project Server. When they try to save a plan,
it's works, but they never receive a confirmation message. It always says 0%
complete expected wait time is 2s. As a result, each time they open MS
Project they have empty projects checked out to you. I have watched, they
are not getting out too soon (unless 1/2 hour after the save was completed,
they should still be wating for the confirmation). I've tried having them
delete the folders under cache too, wth no effect. Most PM's are not having
this problem, so it must be a specific client issue.
Any help would be appreciated. Thanks.
problems between MS Project and Project Server. When they try to save a plan,
it's works, but they never receive a confirmation message. It always says 0%
complete expected wait time is 2s. As a result, each time they open MS
Project they have empty projects checked out to you. I have watched, they
are not getting out too soon (unless 1/2 hour after the save was completed,
they should still be wating for the confirmation). I've tried having them
delete the folders under cache too, wth no effect. Most PM's are not having
this problem, so it must be a specific client issue.
Any help would be appreciated. Thanks.