PS2007- Custom Field Value is not populating

A

Ashish kanoongo

hello

I am using PS2007. I have created a enteprise custom formula field i.e. 'NB'
for Task using following condition
IIf([Task Type]='Non-Billable',[Actual Work]/60,0)

Where [Task Type] is a enterprise text field.

When I open my project in project professional, it is showing and
calculating values in custom field properly. But whenever I open Resource
Assignment Summary, it is showing column, but value is not populating.

Can anyone tell me whats worng I am doing?

FYI, I also rebuild CUBE from server settings also, but no luck.

Ashish
 
J

John

Ashish kanoongo said:
hello

I am using PS2007. I have created a enteprise custom formula field i.e. 'NB'
for Task using following condition
IIf([Task Type]='Non-Billable',[Actual Work]/60,0)

Where [Task Type] is a enterprise text field.

When I open my project in project professional, it is showing and
calculating values in custom field properly. But whenever I open Resource
Assignment Summary, it is showing column, but value is not populating.

Can anyone tell me whats worng I am doing?

FYI, I also rebuild CUBE from server settings also, but no luck.

Ashish

Ashish,
I'm not a Project Server MVP but I think I can answer your question. The
simple answer is that spare task, resource and assignment fields are
independent. For example, if Task Text1 is customized with a formula,
you will not see that formula when you look at Resource Text1 nor will
you see it when you look at Resource Text1.

You might also like to read FAQ 51 - Data Types: Task, Resource and
Assignment, on our MVP website at, http://www.mvps.org/project/faqs.htm

John
Project MVP
 
A

Ashish kanoongo

John

I agree with you, but it should show the value in Resource Assignment
Summary. I also added a another custom field without any formula, in this
custom field it is showing me the values in Resource Assignment Summary.

As per my thinking it should show the formula value also.

Ashish
John said:
Ashish kanoongo said:
hello

I am using PS2007. I have created a enteprise custom formula field i.e.
'NB'
for Task using following condition
IIf([Task Type]='Non-Billable',[Actual Work]/60,0)

Where [Task Type] is a enterprise text field.

When I open my project in project professional, it is showing and
calculating values in custom field properly. But whenever I open Resource
Assignment Summary, it is showing column, but value is not populating.

Can anyone tell me whats worng I am doing?

FYI, I also rebuild CUBE from server settings also, but no luck.

Ashish

Ashish,
I'm not a Project Server MVP but I think I can answer your question. The
simple answer is that spare task, resource and assignment fields are
independent. For example, if Task Text1 is customized with a formula,
you will not see that formula when you look at Resource Text1 nor will
you see it when you look at Resource Text1.

You might also like to read FAQ 51 - Data Types: Task, Resource and
Assignment, on our MVP website at, http://www.mvps.org/project/faqs.htm

John
Project MVP
 
D

Dave

I am not sure if this is the problem but you could try, opening Project Pro,
insert a column with the custom field, see if the values are showing up
properly and then press F9 and then republish the project.

This is a generic trouble shooting tip for graphical indicators.

Hope this helps

Regards,
Dave

Ashish kanoongo said:
John

I agree with you, but it should show the value in Resource Assignment
Summary. I also added a another custom field without any formula, in this
custom field it is showing me the values in Resource Assignment Summary.

As per my thinking it should show the formula value also.

Ashish
John said:
Ashish kanoongo said:
hello

I am using PS2007. I have created a enteprise custom formula field i.e.
'NB'
for Task using following condition
IIf([Task Type]='Non-Billable',[Actual Work]/60,0)

Where [Task Type] is a enterprise text field.

When I open my project in project professional, it is showing and
calculating values in custom field properly. But whenever I open
Resource
Assignment Summary, it is showing column, but value is not populating.

Can anyone tell me whats worng I am doing?

FYI, I also rebuild CUBE from server settings also, but no luck.

Ashish

Ashish,
I'm not a Project Server MVP but I think I can answer your question. The
simple answer is that spare task, resource and assignment fields are
independent. For example, if Task Text1 is customized with a formula,
you will not see that formula when you look at Resource Text1 nor will
you see it when you look at Resource Text1.

You might also like to read FAQ 51 - Data Types: Task, Resource and
Assignment, on our MVP website at, http://www.mvps.org/project/faqs.htm

John
Project MVP
 
A

Ashish kanoongo

Dave

I already did this excercise, but no luck.

Ashish
Dave said:
I am not sure if this is the problem but you could try, opening Project
Pro, insert a column with the custom field, see if the values are showing
up properly and then press F9 and then republish the project.

This is a generic trouble shooting tip for graphical indicators.

Hope this helps

Regards,
Dave

Ashish kanoongo said:
John

I agree with you, but it should show the value in Resource Assignment
Summary. I also added a another custom field without any formula, in
this custom field it is showing me the values in Resource Assignment
Summary.

As per my thinking it should show the formula value also.

Ashish
John said:
hello

I am using PS2007. I have created a enteprise custom formula field i.e.
'NB'
for Task using following condition
IIf([Task Type]='Non-Billable',[Actual Work]/60,0)

Where [Task Type] is a enterprise text field.

When I open my project in project professional, it is showing and
calculating values in custom field properly. But whenever I open
Resource
Assignment Summary, it is showing column, but value is not populating.

Can anyone tell me whats worng I am doing?

FYI, I also rebuild CUBE from server settings also, but no luck.

Ashish

Ashish,
I'm not a Project Server MVP but I think I can answer your question. The
simple answer is that spare task, resource and assignment fields are
independent. For example, if Task Text1 is customized with a formula,
you will not see that formula when you look at Resource Text1 nor will
you see it when you look at Resource Text1.

You might also like to read FAQ 51 - Data Types: Task, Resource and
Assignment, on our MVP website at, http://www.mvps.org/project/faqs.htm

John
Project MVP
 
A

Ashish kanoongo

Dave

I checked in project pro, values are populating properly and also press F9
and republish the project. But no luck.

Ashish
Dave said:
I am not sure if this is the problem but you could try, opening Project
Pro, insert a column with the custom field, see if the values are showing
up properly and then press F9 and then republish the project.

This is a generic trouble shooting tip for graphical indicators.

Hope this helps

Regards,
Dave

Ashish kanoongo said:
John

I agree with you, but it should show the value in Resource Assignment
Summary. I also added a another custom field without any formula, in
this custom field it is showing me the values in Resource Assignment
Summary.

As per my thinking it should show the formula value also.

Ashish
John said:
hello

I am using PS2007. I have created a enteprise custom formula field i.e.
'NB'
for Task using following condition
IIf([Task Type]='Non-Billable',[Actual Work]/60,0)

Where [Task Type] is a enterprise text field.

When I open my project in project professional, it is showing and
calculating values in custom field properly. But whenever I open
Resource
Assignment Summary, it is showing column, but value is not populating.

Can anyone tell me whats worng I am doing?

FYI, I also rebuild CUBE from server settings also, but no luck.

Ashish

Ashish,
I'm not a Project Server MVP but I think I can answer your question. The
simple answer is that spare task, resource and assignment fields are
independent. For example, if Task Text1 is customized with a formula,
you will not see that formula when you look at Resource Text1 nor will
you see it when you look at Resource Text1.

You might also like to read FAQ 51 - Data Types: Task, Resource and
Assignment, on our MVP website at, http://www.mvps.org/project/faqs.htm

John
Project MVP
 
A

Ashish kanoongo

Hello

Can anyone tell whats wrong I am doing, I am stumped. Did everything but no
luck.

Ashish
Ashish kanoongo said:
Dave

I checked in project pro, values are populating properly and also press F9
and republish the project. But no luck.

Ashish
Dave said:
I am not sure if this is the problem but you could try, opening Project
Pro, insert a column with the custom field, see if the values are showing
up properly and then press F9 and then republish the project.

This is a generic trouble shooting tip for graphical indicators.

Hope this helps

Regards,
Dave

Ashish kanoongo said:
John

I agree with you, but it should show the value in Resource Assignment
Summary. I also added a another custom field without any formula, in
this custom field it is showing me the values in Resource Assignment
Summary.

As per my thinking it should show the formula value also.

Ashish
hello

I am using PS2007. I have created a enteprise custom formula field
i.e. 'NB'
for Task using following condition
IIf([Task Type]='Non-Billable',[Actual Work]/60,0)

Where [Task Type] is a enterprise text field.

When I open my project in project professional, it is showing and
calculating values in custom field properly. But whenever I open
Resource
Assignment Summary, it is showing column, but value is not populating.

Can anyone tell me whats worng I am doing?

FYI, I also rebuild CUBE from server settings also, but no luck.

Ashish

Ashish,
I'm not a Project Server MVP but I think I can answer your question.
The
simple answer is that spare task, resource and assignment fields are
independent. For example, if Task Text1 is customized with a formula,
you will not see that formula when you look at Resource Text1 nor will
you see it when you look at Resource Text1.

You might also like to read FAQ 51 - Data Types: Task, Resource and
Assignment, on our MVP website at, http://www.mvps.org/project/faqs.htm

John
Project MVP
 
M

Mike Glen

Hi Ashish ,

You might like to try posting on the server newsgroup. Please see FAQ Item:
24. Project Newsgroups. FAQs, companion products and other useful Project
information can be seen at this web address:
http://project.mvps.org/faqs.htm

Mike Glen
Project MVP



Ashish kanoongo said:
Hello

Can anyone tell whats wrong I am doing, I am stumped. Did everything but
no luck.

Ashish
Ashish kanoongo said:
Dave

I checked in project pro, values are populating properly and also press
F9 and republish the project. But no luck.

Ashish
Dave said:
I am not sure if this is the problem but you could try, opening Project
Pro, insert a column with the custom field, see if the values are showing
up properly and then press F9 and then republish the project.

This is a generic trouble shooting tip for graphical indicators.

Hope this helps

Regards,
Dave

John

I agree with you, but it should show the value in Resource Assignment
Summary. I also added a another custom field without any formula, in
this custom field it is showing me the values in Resource Assignment
Summary.

As per my thinking it should show the formula value also.

Ashish
hello

I am using PS2007. I have created a enteprise custom formula field
i.e. 'NB'
for Task using following condition
IIf([Task Type]='Non-Billable',[Actual Work]/60,0)

Where [Task Type] is a enterprise text field.

When I open my project in project professional, it is showing and
calculating values in custom field properly. But whenever I open
Resource
Assignment Summary, it is showing column, but value is not
populating.

Can anyone tell me whats worng I am doing?

FYI, I also rebuild CUBE from server settings also, but no luck.

Ashish

Ashish,
I'm not a Project Server MVP but I think I can answer your question.
The
simple answer is that spare task, resource and assignment fields are
independent. For example, if Task Text1 is customized with a formula,
you will not see that formula when you look at Resource Text1 nor will
you see it when you look at Resource Text1.

You might also like to read FAQ 51 - Data Types: Task, Resource and
Assignment, on our MVP website at,
http://www.mvps.org/project/faqs.htm

John
Project MVP
 