TroyS
I want to show all of the std earned value calcluations in Data Analysis but
i'm not seeing those calculations available in the Totals of
MSP_Portfolio_Analyzer cube and I don't see it any of the other
NonTimephased cubes.
I know that Project Center has Earned Value and that if i drill into a
Project, I can see the Earned Value at the Task Level.
I wish to do this in Data Analysis as i want to graph such items as BCWS,
BCWP, ACWP and Budget and i want to expand/collapse a project to see tasks
names.
I want to show without having to create a manual calc: SPI, CIP, SV, CV,
Physical % Complete, Budget, BCWS, ACWP, BCWP
How do i get these values to populate the Data Analysis OLAP cube? Any ideas
or directions to links are welcomed...thx.
i'm not seeing those calculations available in the Totals of
MSP_Portfolio_Analyzer cube and I don't see it any of the other
NonTimephased cubes.
I know that Project Center has Earned Value and that if i drill into a
Project, I can see the Earned Value at the Task Level.
I wish to do this in Data Analysis as i want to graph such items as BCWS,
BCWP, ACWP and Budget and i want to expand/collapse a project to see tasks
names.
I want to show without having to create a manual calc: SPI, CIP, SV, CV,
Physical % Complete, Budget, BCWS, ACWP, BCWP
How do i get these values to populate the Data Analysis OLAP cube? Any ideas
or directions to links are welcomed...thx.