PS2007: Earned Value Over Time Report

T

TroyS

Has anyone used this in visual reports?
When i run it, the report's Earned Value, Planned Value and AC don't match
what is in the project schedule..

For example, the schedule shows:

Earned Value (BCWP) = $243,691
Planned Value (BCWS) = $256,935
AC (ACWP) = $256,935

Project Center Earned Value View shows the above numbers

but the visual report shows:
Earned Value (BCWP) = $2,939,500
Planned Value (BCWS) = $3,047,567
AC (ACWP) = $2,939,500

I don't see these values in the project schedule at all; Baseline is only
$710,500 which is nowhere near the $2 million from the report.
Any ideas?
 