T
TroyS
I have a project level field. I've defined the list of values (single list,
no indentation) for the lookup table and i've assigned that project level
field to that lookup table.
For example list = Plan, Analysis, Design, Implement, Close, Retire for a
project level field called Project Phase
When i create a schedule and under Project - Project Information, for that
field i've defined above:
- I don't see all of the values i've created in the lookup table; I see some
but not all.
- Then i see some values in the dropdown from other lists. These values are
not in my lookup table.
- If i edit the schedule from Project Center using Project Properties, I see
the proper list of values.
Has anyone seen before and is this a bug?
Is there a SP for Project Pro 2007?
no indentation) for the lookup table and i've assigned that project level
field to that lookup table.
For example list = Plan, Analysis, Design, Implement, Close, Retire for a
project level field called Project Phase
When i create a schedule and under Project - Project Information, for that
field i've defined above:
- I don't see all of the values i've created in the lookup table; I see some
but not all.
- Then i see some values in the dropdown from other lists. These values are
not in my lookup table.
- If i edit the schedule from Project Center using Project Properties, I see
the proper list of values.
Has anyone seen before and is this a bug?
Is there a SP for Project Pro 2007?