A
Anthony
We are new at implementing MS Project 2007 Server. Within the desktop
application, we are using a simple project update plan (Actual Start,
Actual Duration, Remaining Duration, Actual Finish). I would like to
setup the My Tasks view on the server to allow similar updates. I can
add these fields and they are visible in the view but it does not
allow me to edit the Actual or Remaining Durations. Is there
something I need to change in the configuration to allow these fields
to be "editable" in the My Tasks view? If I use Actual Work and
Remaining Work, those I can change but Work <> Duration. Any
assistance would be appreciated.
application, we are using a simple project update plan (Actual Start,
Actual Duration, Remaining Duration, Actual Finish). I would like to
setup the My Tasks view on the server to allow similar updates. I can
add these fields and they are visible in the view but it does not
allow me to edit the Actual or Remaining Durations. Is there
something I need to change in the configuration to allow these fields
to be "editable" in the My Tasks view? If I use Actual Work and
Remaining Work, those I can change but Work <> Duration. Any
assistance would be appreciated.