D
Donna
Hi -
Does anyone have a formula or a way to just use 1 section of a project
schedule to feed the status indicator that would be displayed in Project
Center.
We've currently got a method in place for ontime/late/overdue - but it looks
at the full schedule.
The project leads in my company - just want to use a milestone section to
indicate status of a project vs the full detailed section.
We want to use fixed work to get this time and drive schedule progress, but
we've been at this for 1 year now and still struggling. Schedules get out of
whack all the time when people actually enter My Tasks work and the Project
center indicators don't reflect reality. Our projects are complex and we
add/remove people, do tasks out of order and change project direction/scope
all the time. This is driving a bit of extra chaos and resistance -- as the
rigid structure of the tool works against the value proposition of the data
that we need to collect. The Project leads are not full time MS Project
experts and we can't affort to just hire project admins. Also -- for now -
they rebelled against Timesheets + My Tasks - seemed to just be duplicate
work for everyone.....
If I could come up with a way for the status indicator to just look at one
section - I would be moving in the right direction.
Thanks for any suggestions....
Does anyone have a formula or a way to just use 1 section of a project
schedule to feed the status indicator that would be displayed in Project
Center.
We've currently got a method in place for ontime/late/overdue - but it looks
at the full schedule.
The project leads in my company - just want to use a milestone section to
indicate status of a project vs the full detailed section.
We want to use fixed work to get this time and drive schedule progress, but
we've been at this for 1 year now and still struggling. Schedules get out of
whack all the time when people actually enter My Tasks work and the Project
center indicators don't reflect reality. Our projects are complex and we
add/remove people, do tasks out of order and change project direction/scope
all the time. This is driving a bit of extra chaos and resistance -- as the
rigid structure of the tool works against the value proposition of the data
that we need to collect. The Project leads are not full time MS Project
experts and we can't affort to just hire project admins. Also -- for now -
they rebelled against Timesheets + My Tasks - seemed to just be duplicate
work for everyone.....
If I could come up with a way for the status indicator to just look at one
section - I would be moving in the right direction.
Thanks for any suggestions....