Hi,

I am trying to create a data analysis view that shows baseline and actual
work of resources in the organization using RBS_Resource dimension. All my
resources are linked correctly to their respective RBS but somehow the
MSP_Portfolio_Analyzer cube does not capture the RBS and resource
relationship. I have even tried a workaround solution by creating a custom
outline field Organization Group and assigned it to the resources, it still
does not work in the MSP_Portfolio_Analyzer.

I have tried using the RBS in Resource timephased and non-timephased cube
and they seems to be working fine.

Thanks and Best Regards
Godrid
 
M

mike.mahoney

Hi,

I am trying to create a data analysis view that shows baseline and actual
work of resources in the organization using RBS_Resource dimension. All my
resources are linked correctly to their respective RBS but somehow the
MSP_Portfolio_Analyzer cube does not capture the RBS and resource
relationship. I have even tried a workaround solution by creating a custom
outline field Organization Group and assigned it to the resources, it still
does not work in the MSP_Portfolio_Analyzer.

I have tried using the RBS in Resource timephased and non-timephased cube
and they seems to be working fine.

Thanks and Best Regards
Godrid

Godrid

Under cube configuration ensure RBS has been added as dimension to all
the cubes.

regards

Mike
 
G

godrid

Hi Mike,

Thanks, it is working now. I did not add RBS to Assignment Cube in the first
place.

Regards
Godrid
 