PS2007 Reporting Inconsistencies between Timesheet, My Task,Unpublished time, and Published time?

A

anovak

Any way to report actual work reported across these areas? Often
times folks forget to import their timesheet into My Tasks. Other
times, they forget to click "Submit All" in My Tasks to submit the
updates. Other times, the manager may forget to accept the Task
Updates. And finally, there might have been an issue with the
publishing process that pushes the newly updated project data to the
published database.

I seem to be able to grab timephased data for Published actual work
and Timesheets, but not for My Tasks and the timephased data in the
Draft database.

Any add-ins out there that provides those data structures if not out
of the box?

Thanks,
Andy Novak
UNT
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top