J
jpa
Hi
(PS2007, SP1, PIU)
let's consider following scenario
- I have a task t1 (fixed work) where users A & B have been allocated 50%
(total t1 work = 40d, 20d for A + 20d for B, t1 duration ~2 months)
=> project pro shows t1: A[50%], B[50%]
- in their timesheets (week granularity) A & B are expected to work 2,5d /week
(lets assume there are 4 weeks for said month, each week having 5 days)
- when filling the timesheet A may report for instance 1d, 4d, 2d, 3d for
each of the 4 weeks of the month (A actually worked 10d as expected for this
month). B is reporting time spent in the timesheet as expected (for the sake
of sample simplicity).
- after updating tasks and accepting tasks updates, when opening Project Pro
I can see t1: A[80%], B[50%], A is in time (10d worked, 10d remaining work)
1) Can you confirm that the 80% comes from the fact that at one moment A has
reported he has worked at 80% (ie the week where he reported 4d)
2) Is this new capacity of 80% used to re-calculate A contribution to task
t1 (& duration) ? (seems not since "AssignmentWork" for this task and
resource is not changed, when looking at Reporting database)
3) My purpose is then to re-consider task scheduling: A is still expected to
contribute 50% to task t1.
So I change A capacity from 80% to 50% (ie t1: A[50%], B[50%]). Modification
is accepted by Project Pro.
I save and close the file.
If I open the file in the follwing minutes, modification still is present
(ie t1: A[50%], B[50%]).
But If I open the file the day after, modification has disapperead and I
still have t1: A[80%], B[50%].
How can this be explained?
Thanks for your help
jpa
(PS2007, SP1, PIU)
let's consider following scenario
- I have a task t1 (fixed work) where users A & B have been allocated 50%
(total t1 work = 40d, 20d for A + 20d for B, t1 duration ~2 months)
=> project pro shows t1: A[50%], B[50%]
- in their timesheets (week granularity) A & B are expected to work 2,5d /week
(lets assume there are 4 weeks for said month, each week having 5 days)
- when filling the timesheet A may report for instance 1d, 4d, 2d, 3d for
each of the 4 weeks of the month (A actually worked 10d as expected for this
month). B is reporting time spent in the timesheet as expected (for the sake
of sample simplicity).
- after updating tasks and accepting tasks updates, when opening Project Pro
I can see t1: A[80%], B[50%], A is in time (10d worked, 10d remaining work)
1) Can you confirm that the 80% comes from the fact that at one moment A has
reported he has worked at 80% (ie the week where he reported 4d)
2) Is this new capacity of 80% used to re-calculate A contribution to task
t1 (& duration) ? (seems not since "AssignmentWork" for this task and
resource is not changed, when looking at Reporting database)
3) My purpose is then to re-consider task scheduling: A is still expected to
contribute 50% to task t1.
So I change A capacity from 80% to 50% (ie t1: A[50%], B[50%]). Modification
is accepted by Project Pro.
I save and close the file.
If I open the file in the follwing minutes, modification still is present
(ie t1: A[50%], B[50%]).
But If I open the file the day after, modification has disapperead and I
still have t1: A[80%], B[50%].
How can this be explained?
Thanks for your help
jpa