My PM would like to know that when he accepts an update from his team
member, how would he be able to determine whether the extra time for a task
will be affecting another project where the team member is also involved in?
The preview function only show how the project will be affected by the update
but not the other project. What is the best way to flag out this information?
Regards
Godrid
My PM would like to know that when he accepts an update from his team
member, how would he be able to determine whether the extra time for a task
will be affecting another project where the team member is also involved in?
The preview function only show how the project will be affected by the update
but not the other project. What is the best way to flag out this information?
Regards
Godrid