J
.jussi
One of my resources recently ran into a very strange problem. One of her
tasks was filled in with actuals over a lengthy period (2+ weeks) with an
even spread of 0.025 hours per day, totaling to 7.5 hours (1 day of work).
She had entered some time towards that task previously, but the task still
had remaining work. The task still has remaining work too - just this one day
of work appeared from somewhere and got spread over the length of the task up
to the current date.
Neither the project manager or the resource can think of anything they've
done that could have resulted in this - has anyone seen behaviour like this
before? Any pointers to where to start the digging?
I will admit that this is not an up-to-date installation. SP2 has not been
applied.
Thank you,
- Jussi
tasks was filled in with actuals over a lengthy period (2+ weeks) with an
even spread of 0.025 hours per day, totaling to 7.5 hours (1 day of work).
She had entered some time towards that task previously, but the task still
had remaining work. The task still has remaining work too - just this one day
of work appeared from somewhere and got spread over the length of the task up
to the current date.
Neither the project manager or the resource can think of anything they've
done that could have resulted in this - has anyone seen behaviour like this
before? Any pointers to where to start the digging?
I will admit that this is not an up-to-date installation. SP2 has not been
applied.
Thank you,
- Jussi