TroyS
Just to be sure i understand what's going on:
1) Timesheet data goes to a timesheet manager for approval and does not go
to the Project Owner (schedule owner)
2) Only Task Updates go to the project owner to approve into the schedule
2a) It appears that the Task Updates does not open up the project schedule
(as it did in PS2003) though there is the Preview function
2b) I can populate my Tasks updates from my Timesheet OR i can populate my
Timesheet from My Task? Do they have to be approved in one before i can
populate the other?
any clarification and/or links to read up on would be helpful as i'm not
seeing what the intention is around Tasks vs. Timesheet updates and How
"best" to use.
thx
1) Timesheet data goes to a timesheet manager for approval and does not go
to the Project Owner (schedule owner)
2) Only Task Updates go to the project owner to approve into the schedule
2a) It appears that the Task Updates does not open up the project schedule
(as it did in PS2003) though there is the Preview function
2b) I can populate my Tasks updates from my Timesheet OR i can populate my
Timesheet from My Task? Do they have to be approved in one before i can
populate the other?
any clarification and/or links to read up on would be helpful as i'm not
seeing what the intention is around Tasks vs. Timesheet updates and How
"best" to use.
thx